Principal Depot Project

Depot workers

Toowoomba Regional Council is constructing a major depot at 24 Nass Road in Charlton. The depot will be a modern, intelligent and sustainable facility to meet the current and future needs of our staff and the communities we serve.

The project includes the construction of a central operations and management building, three workshop buildings, a central store, a nursery and a Toowoomba State Emergency Centre Regional Unit and Toowoomba Group Headquarters.

The new facility will include a number of sustainable design elements focused on water and energy efficiency to minimise the building’s environmental impact.

Preliminary earthworks were completed in early April 2019. Toowoomba-based construction company McNab Developments (QLD) has been awarded the design and construction tender for the project. 

Construction is expected to start in mid-2019 and the depot is expected to open in 2020.

Start date

March 2015

Completion date

2020

Stages

  1. Concept plan and business case – March 2015 to June 2017 (completed).
  2. Design – December 2017 to October 2018 (completed).
  3. Current stage – tender - November 2018 to mid-2019.
  4. Construction – mid-2019 to 2020.