Cambooya trunk sewer main & pump station

Staff in front of pipes

The Cambooya common effluent drainage scheme is being converted to a convention gravity sewerage scheme in a long-term and staged approach. Two related projects that are included in this activity of work are: 

 

Cambooya trunk sewer main

The upgrade of the trunk sewer in Cambooya that takes sewage from the southern area of Cambooya to the Creek Street Sewage Pumping Station (SPS) will continue. The budget allocation for this year's project stages is $250,000 for design and construction works.

Start date

Design work will start in July 2018 with construction commencing some time after that.

Target completion date

June 2019.

 

Creek St sewage pumping station

This project is to upgrade the Creek Street sewage pumping station which pumps sewage from Cambooya to the transfer sewage pump station at Wyreema. The pump station accepts sewage from the southern trunk sewer which is also being upgraded in 2018/19.

The budget allocation for this year's work is $200,000 for design and the commencement of construction works.

Start date

Design work will start in July 2018 with construction commencing some time after that.

Target completion date

July 2020 (staged project over 2 years).