Wyreema (Obst) Park minor earthworks included:

The minor earthworks included improving the earth bunding and profile of the swale drain along the southern boundary of Wyreema (Obst) Park, improving the flood immunity for the properties on the southern sie of the Obst Park.

Earthworks construction was undertaken from Monday to Friday between 6.30am and 6.30pm during a two week period, between late April and June 2021.

Wyreema (Obst) Park improvement works included:

  • construction of new all-access shared paths and connections through the park incorporating the creation of a circuit.
  • upgrade of the primary playground area with new recreation activities and community gathering opportunities.
  • planting native and shade trees.

Park improvement construction was undertaken from Monday to Friday between 6.30am and 5.00pm from March 2021 to June 2021.

Pedestrian access within Wyreema (Obst) Park Walk was maintained where possible during construction. However, access was restricted where there was a risk of harm to the community.

Start date

March 2021.

Completion date

This project was completed June 2021.