Smart water meters project

Project summary The smart water meter project will deliver a Region-wide network of customer water meters that automatically collect water usage figures on a regular basis. This collected data will b...

New Energy Generation project

This project aims to generate energy through our existing land and water assets. We're in the early stages of the long-term project that will take place in multiple stages. In August 2020, we invite...

Clifton packaged water treatment plant

Clifton packaged water treatment plant The Clifton packaged water treatment plant project will deliver a pre-assembled, complete water treatment option for the groundwater aquifer bore system in the ...

Clifton Great Artesian Basin bore project

This project will test the likelihood of artesian bore water being able to contribute to the existing Clifton town water system. The scope includes: The drilling of a test hole and depending on the...

Toowoomba – Vale View pipeline

Vale View is currently supplied by an aquifer bore, however, the decline of the aquifer has posed a water supply issue. A new pipeline will be constructed to connect Vale View to the Toowoomba Bulk Wa...

Jondaryan reservoir upgrade

Jondaryan’s water supply is delivered via the Oakey pipeline and stored in three reservoirs that have a capacity of 45 kilolitres each. To provide sufficient water supply as well as meet the service...

Trunk water main installations - Highfields & Meringandan West

Meringandan West trunk water mains To cater for the growing community of Meringandan West, a new trunk water main will be installed along Highfields Road and Goombungee Meringandan Road. The pipe wil...

Southern trunk pipeline

Southern trunk pipeline A key project of our 2020/21 budget will be the Southern Trunk Pipeline, which will help provide a water security solution for the towns of Clifton, Nobby, Greenmount and Camb...

64 projects make up the $50 million pandemic response investment program

A dedicated $50 million pandemic response investment program has been approved by Council for the 2020/21 financial year. It comprises 64 projects that are being accelerated to stimulate economic acti...

Gowrie Creek trunk sewer upgrade

This project will upgrade and replace the current trunk sewer which was constructed in 1960. Due to age and the nature of sewage, the sewer is in a deteriorated state. In the 2020/21 budget $2.7...

Toowoomba Waste Management Centre vertical expansion- Stage 2

The current landfill cell at the Toowoomba Waste Management Centre will reach capacity in approximately 2 years.  A new landfill cell is required to continue the acceptance of waste at the centr...

Millmerran waste facility upgrade

We're constructing a waste transfer facility at Millmerran as the existing landfill waste facility is nearing capacity.    In the 2020/21 budget $735,000 has been allocated to the project. ...

Yarraman waste facility upgrade

We're constructing a waste transfer facility at Yarraman as the existing landfill waste facility is nearing capacity.    In the 2020/21 budget $420,000 has been allocated to the project. T...

Crows Nest sewage treatment plant planning

A budget of $2 million has been allocated to continue the staged project of converting the Crows Nest CED (Combined Effluent Drainage) scheme to a conventional sewerage scheme. These works are t...

Perseverance raw water main renewal

This project continues the replacement of the 28km long prestressed concrete raw water main from the Pechey reservoirs to the Mt Kynoch Water Treatment Plant over several years. The new pipe...

Pittsworth Waste Management Facility

The existing landfill at Pittsworth is nearing capacity and there is a need for a new facility. To continue providing a waste facility service to the community the existing landfill will be upgraded t...

Kleinton waste facility

We're constructing a waste transfer facility at Kleinton as the existing landfill waste facility has reached capacity. Landfill operations on site will cease and a new waste transfer facility will be ...