Constructed in 1960, the current trunk sewer is in a deteriorated state due to the age and nature of sewage. This project will upgrade and replace the current trunk sewer.

The length of construction is 1,840m with an upgrade in pipe size to allow for increased flows.

In the 2022/23 budget, $300,000 has been allocated to complete works.

Start date

July 2022.

Target completion date

June 2023.