Follow us
Youtube Facebook Twitter Instagram
Toowoomba Regional Council is building a safer, stronger future at Cressbrook Dam through Queensland's largest local government-led dam safety project.
The safety improvements to Cressbrook Dam, including widening the spillway and raising the crest, will ensure the dam can safely pass larger volumes of water in a major flood event. These upgrades are essential to meet modern safety and engineering standards, ensuring the dam can manage future flood risks.
The Cressbrook Dam Safety Improvement Project (CDSIP) is mandated by the Queensland Government Department of Local Government, Water and Volunteers.
The CDSIP is currently in design phase. It is a complex project that carries considerable risk, Council's goal is to do the work once and do it properly. How Council makes Cressbrook Dam safer matters, at its core, this project is about improving water security (through disaster resilience) for the Toowoomba Region community and protecting life downstream. It's too dam important to get wrong!
As part of the design phase, improvement works will be undertaken on three Somerset Regional Council (SRC) roads. The improvements will ensure Kipper Creek Road, Cressbrook Creek Road and Wivenhoe Pipeline Access Road can safely accommodate heavy vehicle movements ahead of major CDSIP construction.
Work has commenced on improving a section of Kipper Creek Road. During this time, one lane will remain open as contractors work Monday to Friday 7.30am - 5.30pm. For everyone's safety, please follow the traffic controller's instructions and the signed speed limit. Work is expected to be completed by the end of 2025, weather and construction conditions permitting.
Toowoomba Regional Council has welcomed the State Government's $54 million funding commitment towards the CDSIP.
Council continues its advocacy efforts with the Federal Government. Earlier this year, Council applied for $97 million in funding from round three of the Australian Government's Disaster Ready Fund 2025-26.
Improving Cressbrook Dam:
Phone: 131 872
Email us with questions or to receive progress updates at: cressbrooksafetyimprovement@tr.qld.gov.au.
12 November 2025: Kipper Creek Road improvement project awarded to local contractor15 September 2025: BOLD edition 48 Spring 12 September 2025: Calls for the Federal Government to commit funding to the Cressbrook Dam Safety Improvement Project23 August 2025: Council expresses thanks to State Government for Cressbrook Dam Safety Improvement Project funding22 August 2025: New campaign launched to highlight Cressbrook project - It's dam important11 August 2025: Cressbrook crossings support fish movements 14 July 2025: Key approval received for the Cressbrook Dam Safety Improvement Project20 June 2025: TRC advancing with the design phase of the Cressbrook Dam Safety Improvement Project 16 June 2025: BOLD edition 47 Winter 20256 June 2025: Cressbrook team shows QPS dam construction site access21 May 2025: Council continuing advocacy efforts for the Cressbrook Dam Safety Improvement Project16 April 2025: Cressbrook Dam gets a ‘Clean Up Australia Day’ touch2 April 2025: Cressbrook team makes early connections with local emergency services24 March 2025: Cressbrook Dam Safety Improvement Project progressing well, meeting Regulator’s current compliance requirements4 February 2025: Council’s priority is Cressbrook Dam in budget submissions15 January 2025: Mayor McDonald highlights TRC’s key opportunities for 202516 July 2024: TRC changes management of water network to lower Cressbrook Dam5 July 2024: TRC delivers Business Case to State Government for Cressbrook19 June 2024: TRC endorses lowering Cressbrook Dam water level for Cressbrook Dam Safety Improvement Project11 June 2024: TRC recommends lowering Cressbrook Dam water level for Cressbrook Dam Safety Improvement Project9 April 2024: TRC announces Cressbrook Dam Safety Improvement Project as state, federal Budget funding priority19 December 2023: TRC announces Seymour Whyte, SMEC to deliver Cressbrook Dam Safety Improvement Project
October 2025
September 2025
August 2025
July 2025
June 2025May 2025
April 2025
March 2025
February 2025
The Cressbrook Dam Safety Improvement Project (CDSIP) is mandated by the Queensland Government Department of Local Government, Water and Volunteers. It is the largest dam safety project undertaken by a Queensland local government to date. Under the guidelines, as a responsible dam owner, Council must achieve an 'As Low as Reasonably Practicable' (ALARP) risk position to increase flood resilience and protect downstream communities.
Toowoomba Regional Council is building a safer, stronger future by protecting life and improving water security at Cressbrook Dam. Yes, this project has been mandated by the Queensland Government, but Cressbrook Dam belongs to the Toowoomba Region; it's community owned infrastructure which carries shared responsibility. The CDSIP will enhance flood resilience, making the dam safer and decreasing the likelihood of failure. It will also protect downstream communities in the Somerset Regional Council area. Industry standards have evolved and so has the level of risk we can responsibly accept as the dam owner. Council is committed to upholding only well recognised, best practice standards, nothing less.
Cressbrook Dam is a referable dam. A referable dam is defined as a dam that poses a potential risk to downstream populations if it were to fail and dam safety standards exist to protect downstream communities.We are applying a risk-based approach to design the safety improvements to ‘As Low as Reasonably Practicable’ to meet the requirements set out under the Water Supply (Safety and Reliability) Act 2008.Council is carefully assessing potential risks, including dam failure and flood impacts, and are evaluating risk reduction measures to determine the most effective solutions.Safety measures are also balanced against factors such as cost, practicality, and environmental impact to find the best solution to ensure safety, efficiency, and sustainability.
Construction work will include:
Other works will include establishing site facilities, preparing local access roads and creek crossings which will be used by the team during construction activities, and restoring areas affected by construction
The team are planning for the CDSIP early construction work to commence by the end of the year, weather permitting.
The following Toowoomba Region roads are anticipated to be used by the project to access Cressbrook Dam (Lake Cressbrook):• Cressbrook Recreation Road• Esk-Hampton Road• Mount Jockey Road• New England Highway• Pechey-Forestry Road• Perseverance Dam Road• Sebastapool Road (enabling works only).The project team will monitor the condition of these local roads.The following Somerset Regional roads may be used by the project to bring equipment and materials to the dam:• Brennan Road• Cressbrook Creek Road• Esk-Crows Nest Road• Gatton-Esk Road• Kipper Creek Road• Toogoolawah-Biarra Road• Wivenhoe Pipeline route
Construction works and impacts
The team will be working Mondays to Saturdays, between 6am to 6pm.Affected residents will be notified before the start of construction and if any work needs to be conducted outside of these hours. The community may experience some temporary impacts, including dust, lighting and noise from machinery or vehicles, and increased traffic or changed traffic conditions on local roads. Where possible, the team will work to minimise impacts and will share information about the progress of the project.Full security measures will be in place on site, including CCTV cameras.
Preparing local Somerset Region roads and creek crossings
To transport materials safely and efficiently to the dam, we are preparing some sections of Cressbrook Creek and Kipper Creek Roads in Biarra that will be used by heavy and light vehicles during the construction phase.We are also preparing identified creek crossings to accommodate any dam water releases that may be needed for constructing this project.
In November 2025, work will commence on improving a section of Kipper Creek Road. During this time, one lane will remain open as contractors work Monday to Friday, 7.30am - 5.30pm. For everyone's safety, please follow the traffic controller's instructions and the signed speed limit. Work is expected to be completed by the end of 2025, weather and construction conditions permitting. We will ensure local landowners and the community are kept up to date on when works are scheduled to begin on Cressbrook Creek Road and Wivenhoe Pipeline Access Road.
Cressbrook Dam's level needs to be at, or below 70 per cent for specific activities during construction. Unfortunately, we can't control the weather, the more rainfall the region receives the longer draw down of the dam will take. Council is preferentially pumping water from Cressbrook Dam for our water supply and have opened the riparian release valves to aid in lowering the dam level.
Cressbrook Dam water level is at 90.72% at August 2025. View the individual dam levels & daily use figures.
For more information see TRC changes management of water network to lower Cressbrook Dam.
63 per cent of the Toowoomba Region’s water storage capacity is at Cressbrook Dam. If it were to fail, not only would it be catastrophic for downstream communities, but it would threaten one of our primary water sources, water our community relies on every day. Safeguarding that supply is essential. The project team have placed high priority on maximising the local spend within the Toowoomba Region to support our community. While we’re not increasing our water storage capacity, this is about protecting our existing water infrastructure.
We encourage local businesses interested in supplying to the project to register an expression of interest through the project's ICN Gateway webpage. For all other procurement or labour hire enquiries, please email cressbrooksafetyimprovement@tr.qld.gov.au or call 131 872.
Please email cressbrooksafetyimprovement@tr.qld.gov.au or call 131 872.
This project is being delivered by Toowoomba Regional Council, SMEC Australia, and Seymour Whyte Constructions.
Please provide feedback to help us improve our site.
Processing your feedback...